Creating in-house popcorn manufacturing capability for WARP

WARP - case study - IFP Construction

Project overview

The refurbishment and remodelling of a live food production site to introduce popcorn manufacturing into an existing snack facility.
NIRAS were responsible for complete design from inception to completion managing both the build and process install and commissioning, with the construction works carried out in-house using IFP Construction.

 

Challenge​

  • Limited budget
  • Short programme expectations
  • Discovery of building issues as project progresses
  • Proximity of existing production operations

Build duration: 6 months

Construction Project value: £4.8m

Total project value £13.6m

Project stage: Completed

NIRAS role: Process & Building Design

IFPC role:  Principal Contractor

Related case studies

Hayden's - case study - IFP Construction

Complete refurbishment and remodel for Haydens

Danish Crown - Case study - IFP Construction

Creating a new manufacturing facility for Danish Crown

Oatly - Case study - IFP Construction

Transforming Oatly’s UK supply chain to deliver their sustainability objectives